Project Location
Wheeler,
OR
Client
City of Wheeler
Market Sector
Project Type
- General Utilities & Infrastructure
Project Disciplines
Project Highlights
- Installed approximately 3,565 linear feet of new 6-inch and 8-inch water main pipes to improve system reliability.
- Constructed a new pressure reducing vault and 4-inch High-Density Polyethylene (HDPE) bore pipe to support improved system performance.
- Completed roadway restoration and repaving following utility construction.
Project Description
The Wastewater System Improvements project upgraded the community’s utility infrastructure by modernizing critical water distribution systems and improving long-term reliability. The project included the installation of approximately 1,615 feet of 8-inch and 1,950 feet of 6-inch C900 PVC water main, along with a new pressure reducing vault and a 4-inch HDPE bore.
Additional improvements included the installation of new fire hydrants and roadway restoration, including repaving portions of existing streets. Together, these improvements strengthened the City’s water system and created more reliable infrastructure for the community.
Work performed by Curran-McLeod, now part of MacKay.